1. Rajasthan Municipal General Purchase and Contract Rules, 1974

  • Basis: Section 298, 80 & 297 of Rajasthan Municipal Act, 1959
  • Total Rules: 17

Rule 1: Short Title & Commencement

  • Short Title: Rajasthan Municipal General Purchase and Contract Rules, 1974 (राजस्थान नगरपालिका सामान क्रय एवं अनुबंध नियम 1974)
  • Commencement: One month after publication in the official gazette (राजपत्र).

Rule 2: Definitions

  • "Board": Includes all three - Municipal Corporation (निगम), Council (परिषद), and Municipality (पालिका).
  • "Purchasing Officer (क्रय अधिकारी) / Requesting Officer (मांग करता अधिकारी)": Refers to the Chief Municipal Officer (CMO).

Rule 3: Purchase of Materials and Execution of Work by Tender

Expenditure Amount (₹)Process
Up to 10KPurchase without quotation
10K - 1 LakhPurchase with three quotations
Above 1 LakhE-Tendering is required

Rule 4: Time Limit for Purchase of Materials

Expenditure Amount (₹)Time Limit (Days)
Up to 1 lakh7
1 lakh - 10 lakh10
10 lakh - 1 Crore15
Above 1 Crore30
  • Starting Point for Time Calculation: Date of publication of the notice in the newspaper.

Rule 5: Re-Tendering

  • If a tender receives an insufficient or inadequate number of bids, re-tendering is required.

Rule 6: Procedure for Obtaining Tenders

Tender SystemDescriptionValue Limit (₹)
Open Tender (खुली निविदा)Public advertisement (सार्वजनिक विज्ञापन)Above 5K
Limited Tender (सीमित निविदा)Direct invitation to a limited number of firmsBelow 10K
Single Tender (एकल निविदा)Invitation to only one firmUp to 1K

Rule 7: Blacklisting

  • The **State Government can blacklist firms/individuals for supplying poor quality materials.
  • Blacklisted firms cannot participate in future tenders.

Rule 8: Ensuring Quality Control

  • Inspection: By Purchasing Officer (CMO) or authorized officer after supply is received.
  • Purchasing Officer is personally liable for ensuring proper sampling.
  • Sample Size: At least 10% of items should be taken for comparison with samples. If less, record the reason.
  • Rejection: If the Purchasing Officer rejects the goods, the supplier bears the cost of returning and replacing the items.
  • Decision Time: Purchasing Officer must decide on acceptance/rejection within 7 days.
  • Stock Register Inspection: Finance Committee members (under Section 283) can inspect stock and purchase registers.
  • Exemptions: The above procedures do not apply to purchases from:
    • Specific organizations
      • राष्ट्रिय कपडा विभाग लिमिटेड
      • राजस्थान हथकरघा परियोजना लिमिटेड
      • राजस्थान राज्य बुनकर संघ
      • राजस्थान राज्य कृषि उद्योग निगम
      • Authorised Khadi Bhandar
      • Cooperative wholesale Upbhokta bhandar
      • Registered Seller with high credibility
    • Authorized repair of fire fighting vehicles from original manufacturer (up to ₹25,000)
    • Spare parts for Motor vehicles (up to ₹1,000)
    • Purchases from Government departments/undertakings
    • When the state government allows exemption
  • Limited tenders may be used for purchases below 10,000 if:
    • Advertising is not in the public interest or
    • The officer certifies the need is emergent.

Rule 9: Charges for Tender Forms

Tender Value (₹)Charge (₹)
Up to 10K20
10K - 1 lakh50
1 lakh - 5 lakh100
5 lakh - 1 Crore200
Above 1 Crore500

Rule 10: Time Limit for Inviting Tenders for Public Works

Construction Cost (₹)Time Limit (Days)
Up to 1 lakh7
1 lakh - 10 lakh10
10 lakh - 1 Crore15
Above 1 Crore30
  • Calculation: From the date of notice publication to the deadline for tender submission.

Rule 11: Publication of Tenders

If estimated cost < ₹2000 Purchase Officer can use Approved Contractor with Rate fixed by PWD.

Estimated Cost (₹)Publication Media
Up to 20KLocal daily, weekly, or fortnightly newspapers approved by the State Government.
20K - 10 lakhProminent daily newspaper of the State.
Above 10 lakhAll-India newspaper and a prominent daily newspaper of the State.

Rule 12: Earnest Money

  • No tender will be considered without the required earnest money deposit.

Rule 13: Inspection Before Approval

  • All goods are subject to inspection before approval. Inspection can occur during manufacturing, before supply, or after supply.

Rule 14: Competent Authority for Approvals

MunicipalityExpenditure Limit (₹)Approving Authority
Municipal Corporation (Nagar Nigam)Up to 25 LakhsAdditional Commissioner (अतिरिक्त आयुक्त) / Deputy Commissioner (उपायुक्त)
Up to 1 CroreChief Executive Officer Cum Commissioner (आयुक्त)
Up to 2 CroreMayor (महापौर)
Up to 5 CroreFinance Committee (वित्त समिति)
UnlimitedMunicipal Corporation (नगर निगम) - Full Powers
Municipal Council (Nagar Parishad)Up to 2 LakhsCommissioner (आयुक्त)
Up to 50 LakhsPresident (अध्यक्ष)
Up to 1 CroreFinance Committee (वित्त समिति)
UnlimitedMunicipal Council (नगर परिषद) - Full Powers
Municipality (Nagar Palika)Up to 1 LakhEO (Executive Officer)
Up to 25 LakhsChairman (अध्यक्ष)
Up to 50 LakhsFinance Committee (वित्त समिति)
UnlimitedMunicipality (नगरपालिका) - Full Powers
  • Important Note: The above authorities exercise powers as per Section 81 of the Act.

  • Exceeding Budget: If actual income/expenditure exceeds the previous year's by more than 20%, approval is required from:

    • State Government (for Corporations and Councils).
    • Regional Deputy Director (for Municipalities).
  • No Increase: Approved administrative and financial sanctions cannot be increased later.

  • Time Limit for Completion:

Cost of Work (₹)Time Limit
Up to 5 Lakhs1 Month
5 - 10 Lakhs2 Months
10 - 50 Lakhs4 Months
50 Lakhs - 1 Crore6 Months
Above 1 CroreDetermined by the Municipal Board
  • Payment Schedule :
Percent of Project CompletionPercentage of Payment Issued
25%12.5%
50%40%
75%75%
100%100%
  • Project Management Consultant (PMC): Can be hired after Board approval if the department lacks resources for a specialized task.
  • Refund of Earnest Money: To unsuccessful bidders within 7 days.
  • Single Tender: May be accepted by Higher Authority if rates are reasonable, but the officer must justify why re-tendering is not in the Board's interest. Normal procedure is to re-tender.

Rule 15: Technical Approval

  1. Technical Committee:

    • The technical committee constituted by the State Government has full powers regarding technical approvals (पूर्ण शक्ति).
    • This committee's approval supersedes the powers of individual officers mentioned below.
  2. Individual Officers and their Powers:

OfficerDesignation AbbreviationSanctioning Limit (₹)Notes
Superintending EngineerSEUp to 1.5 CroreShould come from office of local bodies directorate
Executive EngineerXENUp to 50 Lakhs
Assistant EngineerAENUp to 5 Lakhs
Junior EngineerJENUp to 1 Lakh
  1. Approval Process for amounts greater than 1.5 crore (₹):

    • If The project is of larger value then the officers listed are unable to approve.
    • Any estimate approval must first go to the technical commitee.
    • The technical committee should act on any proposals within seven days.
    • Local office is responsible for officially signing the document to be implemented.
  2. Estimates

    • Estimates must be prepared based on site inspection and the Basic Schedule of Rates (BSR) from the Public Works Department (PWD). This means that for a building to be built, the price is determined from the PWD's documents.
    • The estimate should include:
      • Site plan (स्थल योजना)
      • Design drawings (डिजाइन रेखा चित्र)
      • Structural design (संरचनात्मक डिजाइन)
      • Technical notes (तकनीकी टिप्पणी)
    • Three copies of the estimate must be prepared .

Rule 16: Compliance

  • Contracts are not binding unless they comply with these rules and the Act.

Rule 17: Tender Format

  • The tender format should be in accordance with the Rajasthan General Financial and Accounting Rules.